Callahan Tunnel Open

The Callahan Tunnel officially reopened yesterday, Monday, March 10 at 5am, following months of 24/7 construction that impacted traffic to East Boston and Logan Import.

The $19.3 million contract to McCourt Construction began on December 27 and included additional incentive payments of $71, 500 each day the tunnel opened prior to the advertised date of March 12.

The complete budget for the project, funded through toll revenues, was $25 million revised from the earlier $35 million estimate.

Phil Orlandella

Recent Posts

Four EV charging stations slated for North Street

The demand for EV charging is growing and city officials are gearing up to meet…

2 weeks ago

Tom Brady makes significant gift to Esplanade Association

Thanks to a significant ‘leadership gift’  last week from the family of former New England…

2 weeks ago

Obituary 4-18-2024

Carmela “Millie” (Roberto) DiStefano Known for her heart of gold Carmela “Millie” (Roberto) DiStefano, age 100,…

2 weeks ago

Party in the Park luncheon to take place May 15

The Emerald Necklace Conservancy announces that the 20th Anniversary of Party in the Park, the…

2 weeks ago

City invests in enhanced emergency and coastal resilience planning with floodmap

Special to the Regional Review Mayor Michelle Wu  announced that the City of Boston has…

2 weeks ago

In Brief By Phil Orlandella

NEWRA opposes Mama Maria new lounge/bar By a vote of 8-10 the North End/Waterfront Residents’…

2 weeks ago