North Washington Street Bridge Construction Look-Ahead Through June 12

This is a brief overview of construction operations and impacts for the North Washington Street Bridge Replacement Project. MassDOT will provide additional notices as needed for high-impact work and changes to traffic configurations beyond those described below.

Description of Scheduled Work

•Building the piers:

*Pier 1 (closest to the North End): Column rebar installation and concrete placement.

*Pier 2: V-arms formwork.

*Pier 3: V-arms formwork.

*Pier 4: Installing precast beams.

*Pier 5 (closest to Charlestown): V-arms formwork, rebar installation, and concrete placement.

•Installing, moving, and maintaining silt curtains in the water.

•Installing permanent fender piles.

•Pavement line striping and expanding median at City Square intersection.

Work Hours

•Most work will be done during the daytime (6 a.m. – 6 p.m.)

Work That Has Been Completed

•Prior to 5/30:

*Pier 1 (closest to the North End): Mass-footing rebar installation.

*Pier 2: Mass-footing rebar installation.

*Pier 3: Curing column.

*Pier 4: V Arm concrete placements.

Travel Tips

The Westerly sidewalk, Lovejoy Wharf stairs, near Converse are open to the public with the opening of the temporary bridge, the adjacent section of the Harborwalk passing under the bridge remains closed.

The Tudor Wharf Walkway (under the bridge next to the water in Paul Revere Park) will be intermittently closed for safety during construction operations, with access provided via the Water Street underpass.

North End Regional Review Staff

Recent Posts

Four EV charging stations slated for North Street

The demand for EV charging is growing and city officials are gearing up to meet…

1 week ago

Tom Brady makes significant gift to Esplanade Association

Thanks to a significant ‘leadership gift’  last week from the family of former New England…

1 week ago

Obituary 4-18-2024

Carmela “Millie” (Roberto) DiStefano Known for her heart of gold Carmela “Millie” (Roberto) DiStefano, age 100,…

1 week ago

Party in the Park luncheon to take place May 15

The Emerald Necklace Conservancy announces that the 20th Anniversary of Party in the Park, the…

1 week ago

City invests in enhanced emergency and coastal resilience planning with floodmap

Special to the Regional Review Mayor Michelle Wu  announced that the City of Boston has…

1 week ago

In Brief By Phil Orlandella

NEWRA opposes Mama Maria new lounge/bar By a vote of 8-10 the North End/Waterfront Residents’…

1 week ago