Construction Update: North Washington Street Bridge Construction Look-Ahead Through March 20

This is a brief overview of construction operations and impacts for the North Washington Street Bridge Replacement Project.

Vibratory Hammer Noise Impacts

•A vibratory hammer is being used to install the five cofferdams which will be needed to build the piers of the new bridge. Installation of each cofferdam takes about two weeks.

•The project team has positioned a combination of hanging sound blankets and temporary barrier to minimize noise impacts from the vibratory hammer. These measures will be adjusted as needed and appropriate.

•The vibratory hammer is operated place during the day (7 a.m. – 3 p.m.)

Commercial Street Lane Reduction

•On Saturday, 3/13, there will be a lane closure on Commercial Street to make room for a work zone near the Keany Square section of the project site. The closure will begin at 4 a.m. and end at 7 p.m.

Description of Scheduled Work

•Crews will be repairing warehouse piers and columns, installing, and conducting maintenance of silt curtains, and installing cofferdams.

Work Hours

•Most work will be done during the daytime (6 a.m. – 6 p.m.)

Work That Has Been Completed

•Prior to 3/07/21, Cofferdam installation will be 100% complete.

Travel Tips

The westerly sidewalk, Lovejoy Wharf stairs, near Converse are open to the public with the opening of the temporary bridge, the adjacent section of the Harborwalk passing under the bridge remains closed.

The Tudor Wharf Walkway (under the bridge next to the water in Paul Revere Park) will be intermittently closed for safety during construction operations, with access provided via the Water Street underpass.

North End Regional Review Staff

Recent Posts

Cutillo Park Completion Scheduled for Late Spring To Early Summer

The long-awaited opening of the refurbish Cutillo Park on Stillman Street (weather permitting) is expected…

2 weeks ago

Coletta Holds Hearing on Proposed Legislation Of Property Tax Classification

Special to the Regional Review Boston City Councilor Gabriela Coletta (District 1) chaired a Government…

2 weeks ago

House Passes Bill To Remove Outdated and Offensive Terms

Special to the Regional Review The Massachusetts House of Representatives passed two bills that update…

2 weeks ago

Brian Swett Announced As the City of Boston’s Chief Climate Officer

Mayor Michelle Wu announced the appointment of Brian Swett as the City of Boston’s Chief…

2 weeks ago

News, Notes and Whatever?

NEWRA Committee Reviews Two Requests Two requests, a beer and wine license transfer and a…

2 weeks ago

NEW Health Hosts Viva la Bocce

NEW Health is excited to start a new tradition for the North End neighborhood “Viva…

2 weeks ago